New IJmuiden sea lock delayed by over 2 years, to cost over €60 mil. more

The construction of a new sea lock in IJmuiden will take 27 months longer than expected, public works department Rijkswaterstaat announced on Tuesday evening. Builders BAM and VolkerWessels are again pushing millions more into the construction, ANP reports.

BAM reports a cost overrun of around 30 million euros, VolkerWessels 31.5 million euros. It is now expected that the first ships will only be able to use the sea lock in January 2022, instead of next year.

In December the two construction companies, united in the OpenIJ consortium, announced that the construction of the sea lock needed to be adjusted. Then the two companies jointly pushed another 100 million euros into the project. The initial budget was around 500 million euros.

BAM emphasized that these extra costs to the sea lock will not decrease its profit forecast for this year. VolkerWessels said that the company's gross profit this year will be at the same level as last year, if not slightly higher.

This will be the largest sea lock in the world. Construction on it started in 2016. The lock will be 500 meters long, 70 meters wide and 18 meters deep, and will make it possible for larger ships to dock at the port of Amsterdam.

More like this

Image
Amsterdam homes over a canal
Tech failure very nearly caused massive flood in Amsterdam city center in November 2023
Image
A truck driver lost control on a snowy, icy portion of the A5, prompting the closure of the motorway between IJmuiden and the Raasdorp interchange near Amsterdam's Westpoort area. 2 Jan. 2026
Video: Snowfall, icy roads spell trouble on Netherlands roads; One dead in Rotterdam
Image
Several people use an umbrella to create shade on a scorching hot day after a collision on the A4, June 24, 2026.
Hottest June 24 on record in the Netherlands; Feels like 50°C on the roads
Image
Rijkswaterstaat performing roadworks on a highway
Rijkswaterstaat extends nationwide heat measures, postpones A12 roadworks
Make NL Times your top Google source

Follow us:

Latest stories

  • Landlords ignore rent tribunal rulings in at least 10 percent of cases
  • Hottest June 24 on record in the Netherlands; Feels like 50°C on the roads
  • Heatwave: Defqon.1, TT Assen ready for 38°C days; More events cancelled
  • Hundreds of thousands of Dutch use Ozempic to lose weight; Third without prescription
  • Controversial FVD-affiliated school reopens with state funding confirmed

Top stories

  • Six arrested in electoral fraud investigation; Allegations of forgery, voter coercion
  • Hottest night on Dutch records expected tomorrow; Code Orange takes effect at noon
  • 270 children abducted to or from the Netherlands last year; Increase of over 25%
  • Public transport strike from 4 a.m. to 8 a.m.: No trains, buses, trams, metros running
  • Life sentence sought for Dutch-Rwandan man over massacre of 3,000 Tutsi in 1994 genocide

© 2012-2026, NL Times, All rights reserved.

Footer menu

  • Change Privacy Settings
  • Privacy Policy
  • Contact
  • Partner Content